An external lift for a listed heritage building: the Chernivtsi example

The Chernivtsi Regional State Administration building is a monument of national significance. How we added a glass shaft on its own foundation to the courtyard façade, turned windows into doorways and installed an Izamet panoramic lift without a single new opening through the historic wall.

  • 6min read

Updated

Courtyard of the regional administration building with the glass shaft of a panoramic lift attached to the facade

In September 2026 we handed over a project in Chernivtsi that had taken us two years: an external panoramic lift for the building at 1 Hrushevskoho St. It houses the Regional State Administration and the Regional Council, and the building itself is an architectural monument of national significance, heritage register No. 1740. The client, the municipal "Directorate for the Maintenance of Jointly Owned Property of Territorial Communities", wanted a wheelchair user, a mother with a pushchair or a visitor with bad knees to reach each of the four floors by lift rather than by the stairs. In a listed building, that is a story of its own.

Inside a listed building you cannot cut a lift shaft without damaging the floor slabs and stairwells, so from the outset there was only one option: to put the lift outside.

Why the lift is in the courtyard

We did not even consider the main facade on Hrushevskoho Street. The courtyard facade was possible, but only with care: the new structure stands on its own foundation and is fixed to the historic wall at isolated points only. That is how the shaft was designed: a free-standing steel frame that adjoins the courtyard facade and is tied to it by just a few connections, only where they cannot be avoided.

For the building, this means the weight of the shaft and the lift does not bear on the old walls and floors. For us, it meant almost everything was done from outside, and we only went inside for the door openings and the radiator recesses.

Foundation, pit and frame

At the bottom is a dedicated foundation on bored piles: holes up to 630 mm in diameter were drilled next to the old foundations, and each one was inspected together with the technical supervisor before being concreted. Below the car is a waterproofed pit: water must not be allowed near the foundations of a listed building, as that would be a problem for the building itself.

Above that is the frame. The dark steel sections carry both the glazing and the lift guide rails, so the tolerances here are lift tolerances rather than building ones: millimetres over the full height of four floors. The frame was aligned over its entire height and only then clad in glass. The shaft has its own roof, so neither rain nor snow gets in.

The glazing is continuous, from a low steel plinth up to the roof. From the courtyard it is simply a glass shaft beside an old wall, with no attempt to make it look historic. There are no doors from the courtyard into the shaft: people enter the lift from the building's corridors on each of the four floors.

Doors in place of windows

The most delicate work was in the wall. To get from the lift to the second, third and fourth floors you need door openings, and nobody wanted to cut new openings in the wall of a listed building. The doors were made in place of windows that already faced the courtyard opposite the shaft. The glazed frames were carefully removed and kept, the wall below the sills was taken down to floor level, and not a single new through-opening appeared in the historic wall: the windows simply became doors. Recesses for the heating radiators were made alongside.

What is in the shaft

An Izamet panoramic lift with a rated load of 630 kg, a speed of 1.0 m/s and four stops. The car is glazed on three sides: passengers see the courtyard and the opposite facade with its carriage archway, and the car can be seen from the courtyard. In a transparent shaft everything that is normally hidden behind walls is on show (guide rails, cable routes, lighting), so the quality of the installation is visible to everyone.

We supply, install and maintain Izamet lifts in Ukraine. Before handover, the lift went through commissioning and testing: safety gear, overspeed governor, buffers, brake, stopping accuracy to DSTU EN 81-20, test runs and dynamic tests at rated load.

Two contracts and two years

The work was done in two stages, and both can be checked in Prozorro using our EDRPOU code 33860532. The first contract, from 2024 (UA-2024-08-05-011578-a), opened the project: pit, steel-frame shaft, lift installation. The second, No. 2L of 23 July 2026 (UA-2026-06-26-011590-a), closed it: bored piles for the shaft foundation, door openings on the second to fourth floors, shaft roof, electrical installation and earthing, commissioning and handover. In total, over UAH 10.3 million. Almost two years passed between the contracts: on a listed building the paperwork sometimes takes longer than the installation.

Takeaways for clients

  • If a building has protected status, an external shaft is often the only realistic way to make it accessible. Inside a listed building there is usually nowhere to put a shaft without damaging the building.
  • Budget for the extension, not the lift. The cost estimate will include the foundation, pit, wall survey, calculations for the fixing points and restoration approval, and the lift itself is just one line on that list.
  • Timescales are set by approvals, not by installation. Plan your time around the paperwork, not the frame and the lift: on a project like this, it takes longer.
  • Glass neither imitates the old fabric nor competes with it, and that is an argument for both the architect and the heritage protection authority.
  • Budget benchmark: over UAH 10.3 million across two contracts for piles, pit, shaft, glazing, lift and commissioning.

We take on projects like this in full: the survey, arranging the design and approval by the cultural heritage protection authority, expert review, steel frame, glazing, lift and commissioning. If you have a building with protected status and the stairs have long been a problem, we will come, take a look on site and tell you whether there is room for a shaft.

Quick answers

Related questions

Can a lift be added to any listed building?

Not to any building, and not on any side. Main facades are usually off-limits; courtyard facades are subject to approval. The decision is made by the cultural heritage protection authority on the basis of the design, so the survey and the design come first, and only then do we give timescales.

How long does such a project take?

In Chernivtsi, two years passed between the first contract and handover, and a large part of that time was taken up not by work on site but by the gap between the two contracts. We cannot honestly say how much of it went on the installation itself: the work was done in two stages with a break in between.

Who maintains the lift after handover?

Maintenance is a separate contract, and we offer it on every project we deliver. A panoramic lift in a glass shaft needs the same scheduled maintenance as a conventional one, plus care of the glazing and seals.

Read next

Metron lifts from Greece: the series available and who they suit

Metron from Serres: machine-room-less lifts, series with a pit from 550 mm for older buildings, hydraulic lifts, home lifts and steel shafts. What to know before ordering.

Canny escalators: who the manufacturer is and where they are already in service

Canny Elevator escalators and moving walks for shopping centres, railway stations and metros. How many are produced, which projects the manufacturer showcases and how we choose a model for a building.

MP Mobi home lift: a hydraulic platform lift with car doors

MP Mobi is a vertical platform lift from Spanish manufacturer MP that works like a regular lift (elevator): car doors, one-touch call, pit from 200 mm, up to 1000 kg, battery-powered rescue. Who it suits and where its limits lie.

MP lifts from Spain: who the manufacturer is and why we recommend it

MP lifts from Seville: in-house electronics and traction machines, an open (non-proprietary) controller, EU certificates, two factories. What we check in a manufacturer before offering it to clients, and what ordering an MP lift with installation and service from Portal looks like.

A lift for a private house: the options and what the building decides

A chair stair lift, a home lift with no pit, a PVE pneumatic lift, a Cibes screw-driven platform lift or a hydraulic lift: which of them will actually fit in your house.

The lift has stopped: what passengers, neighbours and the homeowners' association chair should do

What to do when a lift stops: how to act inside the car, why you must not open the doors, who is authorised to carry out a rescue, and what the homeowners' association (OSBB) can do to stop it happening again.

Lift options: what to order up front and what can be added later

A walk through a lift quotation: which options must be planned before installation, which can be added later without rework, and which are worth skipping.

How to choose a lift: a step-by-step guide for clients

What determines the choice of lift: building type, number of floors, rated load, drive type and whether there is a machine room. Practical guidelines and common mistakes.

Lift modernization or full replacement: which to choose

When replacing individual lift components is enough, and when a new lift is cheaper. Decision criteria, timelines and what happens to the shaft.

Lift shaft: dimensions, pit and headroom

Lift shaft plan dimensions, a 1200-1400 mm pit and 3600-4000 mm headroom for a 1.0 m/s lift, and when 50-150 mm is enough. What to measure before pricing.

Glossary of lift terms

What pit, headroom, safety gear, counterweight, group control and other terms found in lift equipment designs and contracts mean.

Lift car design and finishes

What lift cars are made of, which finish options are available and how to choose materials for the building type and intensity of use.

How much lift replacement costs and what makes up the price

Why the price is not quoted over the phone, which items actually make up the cost of a lift replacement, what drives the cost up and which benchmark you can check in the open register.

We'll price your equipment free of charge

Choose what you need: an engineer will contact you within one working day, select a model and calculate the cost.

Or leave your number and we'll call you back

We'll call you within one working day. The site survey and pricing are free of charge.

Or just give us a call: +38 (050) 585-39-28 ·+38 (063) 283-31-48 ·+38 (096) 901-76-50